How Long Does a Commercial Window Replacement Take?

Commercial window replacement takes 6-12 weeks total. Learn exact timelines for each project stage, from survey to completion, in our UK facility manager guide.

Back To Blog
How Long Does a Commercial Window Replacement Take?

Table Of Contents

Most commercial window replacement programmes run between six and twelve weeks from instruction to completion, but the honest answer is that the survey sets the programme, not the window count. This guide explains what each stage depends on so you can tell a realistic programme from an optimistic one. GLRE delivers commercial window refurbishment and replacement across the UK.

‍

What actually drives the timeline?

‍

  • The glass specification, and whether it is a stock product or made to order.
  • Access: ground-level work, a platform, a scaffold or rope access are four different programmes.
  • Whether the building is occupied, and what that does to working hours.
  • How many elevations can be worked at once without compromising weather protection.
  • Whether the existing frames stay or go.
  • Approvals, particularly on listed buildings and in conservation areas.
  • The weather, which affects lifting more than it affects labour.

‍

How long does the survey and planning stage take?

‍

Usually the shortest stage in calendar terms and the most important one. A site survey records the existing units, the frames, the fixings, the access constraints and the condition of what is being kept, and everything downstream is priced and programmed from it.

‍

This is also the stage a client can shorten, by making the specification decision quickly. See glazing inspections.

‍

How long does manufacture and procurement take?

‍

This is normally the largest single block of time in the programme and the one nobody expects. Sealed units are made to the sizes taken off the survey, which means nothing can be ordered until the survey is complete and the specification is signed off.

‍

Stock sizes and standard specifications come through fastest. Toughened, laminated, fire-rated, acoustic, coated and oversized units all take longer, and anything requiring a bespoke profile or a discontinued section takes longer again. Where an original profile is no longer available, it may have to be manufactured, as it was on the Heathrow programme.

‍

How long does access take to set up?

‍

It depends entirely on the method, and this is where the biggest programme differences come from.

‍

  • Ground and low-level work: effectively no set-up.
  • Mobile elevated work platforms: short, subject to ground conditions and permits.
  • Rope access: fast to mobilise and well suited to occupied buildings. See rope access glazing.
  • Scaffolding: the longest lead time by a wide margin, and it has to come down again at the end.

‍

The selection logic is set out in how access is planned for high-level glazing. All work at height is planned under the Work at Height Regulations 2005.

‍

How long does installation take?

‍

Per window, a straightforward like-for-like unit swap at low level is quick. The same unit at height, oversized, or requiring frame repair before the new unit goes in, is not.

‍

Rather than quoting a daily rate, ask the contractor for a rate specific to your building, taken from the survey, and ask what assumptions it depends on. A day rate with no assumptions attached is a guess with a decimal point. See commercial glass replacement process.

‍

Does weather affect the programme?

‍

Yes, mainly through lifting. Wind is the limiting factor: a large glass panel is a sail, and the safe working limit depends on the panel size, the lifting method and the equipment manufacturer's stated limits rather than on a single figure.

‍

Rain affects sealant application and curing. Cold affects both. Winter programmes should carry more contingency than summer ones, and a contractor who does not say so is not planning for the weather you will actually get.

‍

How does building size change things?

‍

Less than people expect, because the fixed stages do not scale. Survey, specification, procurement lead time and access set-up are broadly the same for twenty windows as for two hundred. What scales is the installation itself.

‍

That is why small programmes often feel disproportionately slow and large ones disproportionately efficient. For larger schemes, see how to plan a window replacement programme.

‍

Can the programme be accelerated?

‍

  1. Decide the specification early. Nothing can be ordered until it is fixed.
  2. Survey early, even before the budget is approved, so the lead time starts sooner.
  3. Work more elevations at once, where access and weather protection allow.
  4. Extend working hours, where the building and the local authority permit it.
  5. Accept a stock specification where the performance requirement allows it.

‍

What cannot be compressed is manufacture. Acceleration costs money and the premium should be quoted for your project rather than read off a web page.

‍

How is disruption managed in an occupied building?

‍

  • Phase by elevation or floor, so only one area is affected at a time.
  • Maintain weather protection progressively, so no part of the building is ever open to the weather overnight.
  • Use rope access where a scaffold would block entrances or trading frontage.
  • Agree working hours around the building's use: term dates, trading hours, clinical schedules.
  • Give occupants a programme, and update it when it changes.

‍

Does the work need Building Regulations approval?

‍

Replacing glazing can bring the work within the Building Regulations. In England the relevant guidance includes Approved Document K for impact protection and glazing in critical locations, together with the approved documents covering fire safety and conservation of fuel and power. The current set is listed at the current Approved Documents.

‍

Check which approval route applies before you start. Replacement glazing can be self-certified under a Competent Person Scheme in some circumstances and needs a building control application in others, and the schemes for buildings other than dwellings specifically exclude load-bearing structural glass, glazed curtain walling and revolving doors. The authorised list is at the authorised Competent Person Schemes.

‍

Approval routes affect the programme, so settle them at survey stage rather than discovering them at installation. Where the assessment concludes the existing system can be kept, see refurbishment against replacement, commercial glazing refurbishment and commercial glass replacements. High-level work is covered under high-level glass replacements.

‍

Need a programme you can hold a contractor to? Book a survey and we will give you dates from your building.

‍

No items found.

Our Services

GLRE offers expert commercial glazing services, including high-level glass replacements, commercial window refurbishment and replacement, and emergency glazing solutions.
Explore Services

Get a Free Site Survey

Our experts are ready to assess and recommend maintenance, repair, or replacement options. Schedule your survey today with the UK's leading glazing company.
Book Now